Pile level correction (Commencing late March and scheduled to conclude late April 2026)
- Pile trimming to correct levels using Stihl sawing methods.
- Works planned and sequenced to minimise duration and overall disturbance.
- A gravity-fed water suppression system will be deployed throughout to control dust emissions.
- Noise monitoring will continue in line with the Best Practicable Means (BPM) as defined under BS 5228.